Builder delay lawyer in Bangalore: RERA refund and interest
What a homebuyer can do when a Bangalore builder misses the possession date: Section 18 of RERA, refund, interest and the forums involved.
When a builder or promoter misses the possession date in the agreement for sale, a homebuyer has statutory options under the Real Estate (Regulation and Development) Act, 2016 (RERA). This guide explains them in plain terms. It is general information, not advice on a particular project.
The choice under Section 18
An allottee can withdraw from the project and claim a refund of the amount paid with interest, or stay in the project and claim interest for every month of delay until possession. The Supreme Court, in Newtech Promoters and Developers v. State of Uttar Pradesh (2021), described the refund right as indefeasible where possession cannot be given as agreed.
Interest
In Karnataka, the rules set the rate by reference to the State Bank of India's highest marginal cost of lending rate plus two per cent.
Where to go
- K-RERA (the Karnataka Real Estate Regulatory Authority) decides complaints for refund and interest.
- The Adjudicating Officer decides compensation.
- Appeals go to the Karnataka Real Estate Appellate Tribunal, and then to the High Court of Karnataka.
What to keep
The agreement for sale, the allotment letter, every payment receipt, the project's RERA registration details and any correspondence with the builder about delay.